homeproject details | construction | news room | operations | history | corporate info | contacts | sitemap    
   
  eNews
 
Home > News Room > eNews
 
Navigation goes here.


Traditional owners and locomotive naming ceremony in Katherine September 02


Tracklaying process - placing sleepers under rail


Victoria Highway overpass near Katherine September 02
X ADrail/APT


Placing of Bridge girders on Elizabeth River
Railway Bridge
September 2002
X ADrail/APT


Adelaide River Railway Bridge
NOTE: Old railway bridge on left and road
bridge on right of railway bridge
September 2002
X ADrail/APT


Reburbishment of original Fergusson River
Railway Bridge for use on new line. Adjacent
Bridge is the road bridge.
September 2002
X Videocraft


Crossing of the new Katherine River Railway Bridge
September 2002


Tracklayer crossing bridge north of Katherine

   

WELCOME TO RAILWAY eNEWS - 8 November 2002.

IN THIS EDITION:


MILESTONES & EVENTS
Since our last eNews quite a few milestones have been achieved:

  • Over 50% of the Minor Bridges on the railway line were completed in August.
  • Major Bridges over the Katherine, Edith and Cullen Rivers were completed.
  • The Victoria Highway overpass and Stuart Highway overpass near Katherine have been completed and are open to traffic.
  • Production of Ballast exceeded 50% of total requirements during August.
  • Overall construction is progressing well and during September exceeded the 50% mark.
  • Clearing of the corridor is well advanced with the Adelaide River Section completed in September and clearing teams from the North and South meeting near the Buchanan Highway south of Katherine.
  • Delivery of rail from One Steel in Wyhalla reached 50% of project requirements.
  • Rail track has been laid for 33% of the entire route.
  • Track was laid over the Katherine River Bridge to reach the ballast quarry north of town.

The next major event will be the joining of the two tracks between Katherine and Tennant Creek. It is expected that this will take place in mid December so please keep an eye on our website for updated information.

CONSTRUCTION HIGHLIGHTS
The Construction Progress Map has been updated recently to give an overall picture of where ADrail are progressing

A few high-lights are:

Katherine
On 17 September the tracklayer headed north laying track across the new Katherine River Railway Bridge to the ballast quarry 20 kms north of town. More information

Locomotive Naming Ceremonies were held in Katherine and Tennant Creek in September with the participation of Traditional Owners.

ADrail recently held an open day to give the people in the Katherine area a close up look at construction and tracklaying.

The latest employment figures show 276 Katherine residents are directly employed on the construction of the railway.

245km of track is now complete to the south of the town and 28 kms north.

Alice Springs
Over 81,000 tonnes of rail has so far been delivered to the Roe Creek Logistic Centre by rail from OneSteel Whyalla SA then trucked north to Tennant Creek and Katherine.

The latest employment figures show 60 Alice Springs residents are directly employed on the project.

Tennant Creek
Latest employment figures show 227 Tennant Creek residents are directly employed on the construction of the railway.

950,000 tonnes of ballast has been produced locally.

Darwin
Bridge piling is now completed on the largest bridge, the Elizabeth River Bridge and bridge girders are in the process of being placed, with over 50% complete.

Bulk earthworks have been completed on the railway causeway and container terminal site at East Arm Wharf at the Port of Darwin.

98% of clearing and 84% of earthworks are now complete between Darwin and Adelaide River.

Refurbishment of the Fergusson River Railway Bridge from the original North Australian Railway has been completed.

Latest employment figures show 353 Darwin residents are directly employed on the construction of the railway.

South Australia
At present 147 South Australians are directly employed on the construction of the railway.

South Australia industry has so far been awarded contracts valued at over $311 million.

PHOTO LIBRARY
The photo library has been and will continue to be updated with photos of construction as well as recent events, including the crossing of the Katherine River Bridge, ADrail Open Day and Locomotive Naming Ceremonies.

We have had a few requests for video footage of tracklaying and construction and we are currently looking into the possibility of making short movie clips available from our website.

LATEST PROGRESS MAP AVAILABLE NOW
The latest progress map is now available. Since our last eNews we have updated our progress map pages as some people were having difficulty accessing the map with Acrobat. There are now several options to view and print the map, but if you are still having difficulty, please let us know.

JOINING OR LEAVING THE RAILWAY eNEWS LIST
If you would like to join our eNews list or know others who would like to join the Railway eNews list, they can join through our website or by sending us an email at rail@aarc.com.au and place word SUBSCRIBE in the subject field. If you no longer wish to receive updates through the Railway eNews, please send us an email and place the word UNSUBSCRIBE in the subject field.

PRIVACY
Your Privacy is important to us. No names or details in our eNews mailing list are shared with other organisations or used for any purpose other than to provide updates on the railway project and related issues

 

© AustralAsia Railway Corporation Disclaimer/Privacy/Copyright Statement
For text based navigation please use the sitemap | Interpreter service
Last updated:
Friday, 2 May, 2003
Telephone 61 8 8946 9595 Search NTG homepage Online services News Sitemap Feedback