homeproject details | construction | news room | operations | history | corporate info | contacts | sitemap    
   
  eNews
 
Home > News Room > eNews
 
Prime Minister John Howard discusses the progress of the project with AustralAsia Railway Corporation's Deputy CEO Brendan Lawson (left) and ADrails Project Director Al Volpe

Prime Minister Howard talking with ADrail's Northern Tracklaying crew near Adelaide River 5 August 2003

Tracklayer progressing across the
Adelaide River Bridge

Tracklayer passing the old Adelaide River Railway Station - 29 July 2003

Looking north across Adelaide River Bridge
(note the old railway bridge on left) - 29 July 2003

Public on south bank of Adelaide River awaiting
tracklayer - 29 July 2003

Tracklayer reaches the north Abutment of the
Adelaide River Bridge - 29 July 2003

Looking north across Adelaide River Bridge
(note the old railway bridge on left) - 29 July 2003

Tracklayer on the Adelaide River
Railway Bridge-September 02


 

    WELCOME TO RAILWAY eNEWS. - 8 August 2003

IN THIS EDITION:


PROJECT NEWS

  • As part of his trip to the Northern Territory, Prime Minister John Howard inspected tracklaying activities and spoke with ADrail workers at Adelaide River. (see story)
  • The Northern Territory Government has launched an education campaign aimed at raising the awareness of community responsibilities in upholding the highest level of safety at railway crossings. (see NTG Media Release)
  • Although construction of the track is expected to be completed by the end of October 2003, there will be completion and commissioning processes and procedures that need to be carried out in order for the line to be declared 'fit for purpose', once completed, commercial operations can then begin.
  • On 17 June FreightLink released the date for their inaugural freight train to Darwin arriving on 17 January 2004, with GSR's announcement several days later their inaugural passenger train will arrive in Darwin on 3 February 2004. Further details about the AustralAsia Railway's inauguration and the series of celebrations will be made available in the coming months, please check our website for updated information. (more info)
  • Over the next few months, tracklaying will be completed over the full length of the railway line, a few of the forthcoming milestones of completion are:
    - the final flash butt weld of short welded rail into long welded rail sections,
    - the last rail delivery from OneSteel in South Australia to Katherine and Tennant Creek,
    - the last concrete pour of sleepers at Katherine and Tennant Creek Sleeper Manufacturing Plants,
    - the joining of the track from Tarcoola to the new section in Alice Springs, and
    -the completion of Tracklaying at the Port of Darwin.
  • An international freight symposium will be held in Darwin on 9 and 10 February next year to coincide with the start of railway operations on the AustralAsia Trade Route. (more info)


CONSTRUCTION HIGHLIGHTS

Progress on construction of the railway is proceeding well with only 190 km of track to be laid, 83 km to Alice Springs and 107 km to Darwin (to 29 July). Tracklaying is scheduled for completion by October, when testing on the line will be undertaken before it is ready for commencement of regular scheduled services in January 2004. Highlights of construction since the last eNews include:

  • The completion of clearing and embankment construction,
  • The completion of all Grade Separate Crossings (overpasses),
  • The construction of level crossings in the Darwin area,
  • The commencement of construction on buildings at the Berrimah Yard, and
  • The crossing of the Adelaide River Bridge. (see story)

  • The Construction Progress Map at http://www.aarc.com.au/aarc/info/progress.html has been updated with statistics quoted to the 29 July - A few highlights are:

Darwin

  • Latest employment figures (to 30/6/03) show 136 Darwin residents are directly employed on the construction of the railway.
  • The completion of construction of level crossings between Adelaide River and Darwin prior to the commencement of tracklaying, signalling works will be completed over the coming months and crossing signals will become operational as the tracklayer progresses towards Darwin.
  • Tracklaying in the ARR section (between Adelaide River and Darwin) commenced in late July with the Adelaide River Railway Bridge crossed on 29 July. (see story)
  • The Stuart Highway overpass south of Adelaide River (KR190) was completed and opened to traffic.
  • Earthworks continued within the Berrimah Yard area and are currently meeting production quantities. Steelworks on the locomotive workshop and refuelling buildings were completed.
  • The NT Government and its consultant are proceeding with design of the passenger terminal and storage siding at Berrimah and earthworks on the NT Government's Business Park are well advanced.
  • Construction at the East Arm Wharf development is continuing, including the relocation of the container crane from the Fort Hill Wharf. (see NTG Media Release). For details on progress of all components of the works, see DIPE Factsheet at http://www.nt.gov.au/ipe/dtw/projects/factsheets/EastArmWharf.pdf

Katherine

  • The latest employment figures (to 30/6/03) show 127 Katherine residents directly employed on the construction of the railway.
  • Tracklaying was completed in the KR Section (between Katherine and Adelaide River) in late July and commenced in the ARR section.
  • Sleeper production is 98% complete with 920,500 of the required 943,200 sleepers produced.
  • Flash Butt rail welding continues with 37,614 welds complete.


Tennant Creek

  • Latest employment figures (to 30/6/03) show 125 Tennant Creek residents directly employed on the construction of the railway.
  • Tracklaying south from Tennant Creek is complete to 392 km with only 83 km remaining to be laid to reach Alice Springs
  • Production of sleepers from the Tennant Creek Depot reached 1,027,200 (98%.


Alice Springs

  • Approximately 144,000 tonnes of rail has so far been delivered to the Roe Creek Logistic Centre by rail from OneSteel Whyalla SA to be trucked north to Tennant Creek and Katherine depots.
  • Construction of the Stuart Highway overpass north of Alice Springs (ASR17) was completed in June and opened to road traffic.
  • The latest employment figures (to 30/6/03) show 37 Alice Springs residents directly employed on the project.

South Austraila

  • At present (to 30/6/03) 64 South Australians are directly employed on the construction of the railway.
  • South Australian industry has so far been awarded contracts valued at over $347 million.


LATEST PROGRESS MAP AVAILABLE NOW
The latest progress map is available on our internet site at http://www.aarc.com.au/aarc/info/progress.html


JOINING OR LEAVING THE RAILWAY eNEWS LIST
If you no longer wish to receive updates through the Railway eNews, please return this email and place the word UNSUBSCRIBE in the subject field.

If you know others who would like to join the Railway eNews list, they can join through our website at www.aarc.com.au or by sending us an email at rail@aarc.com.au and place word SUBSCRIBE in the subject field.


PRIVACY
Your Privacy is important to us. No names or details in our eNews mailing list are shared with other organisations or used for any purpose other than to provide updates on the railway project and related issues.

 

© AustralAsia Railway Corporation Disclaimer/Privacy/Copyright Statement
For text based navigation please use the sitemap | Interpreter service
Last updated:
Friday, 2 May, 2003
Telephone 61 8 8946 9595 Search NTG homepage Online services News Sitemap Feedback