WELCOME TO RAILWAY eNEWS - 16 January 2003

IN THIS EDITION:


MILESTONES & EVENTS
The last few months have been a very exciting and busy time for the project with several major announcements and achievements. 

  • The completion of clearing and drainage in KR Section during December brings the total to 80% of project requirements.
  • Earthworks have been completed on Stuart Highway overpasses south of Adelaide River and south of Tennant Creek. See Progress Map
  • Production of sleepers exceeded 50% of project requirements at the Tennant Creek Sleeper Plant.
  • Tracklaying by the Northern Tracklaying crew (operating out of Katherine) exceeded 50% complete.
  • The final beams were installed on the Elizabeth River Bridge (the largest on the project) in December.  This major bridge is now structurally complete along with those at Adelaide River, Cullen River, Fergusson River, Edith River and Katherine River. more info
  • ADrail completed the rehabilitation of the Gouldian Finch wet season feeding habitat with the assistance of Greening Australia and Aboriginal workers from the Kybrook Aboriginal Community.
  • On 5 December 02, the NT Government announced it would spend $9 Million on a Business Park in the East Arm Development Area to complement the East Arm wharf precinct and the railway.  See NTG media release
  • Katherine has the potential to play a major role in the Territory's import and export networks and a workshop to evaluate Katherine as a road and rail hub was held on 12 December.  NTG Media Release
  • On 13 December 02, the section of track between Katherine and Tennant Creek was completed with a ceremony taking place to commemorate the final thermit weld on this section.  For more information see the Thermit Weld page on our website.
  • On 16 December 02, the NT Government announced the location of passenger terminals in the NT. See links to pictorial images on News Room and NTG Media Release
  • 14 January 03 - Announcement that EDI Rail have been awarded a $60 million contract to supply and maintain locomotives and container wagons.  Downer EDI Media Release. See also SA Premier Media Release

CONSTRUCTION HIGHLIGHTS
The Construction Progress Map has been updated recently to give an overall picture of where ADrail are progressing. Previously some viewers were having difficulty accessing the map with Acrobat.  There are now several options to view and print the map, but if you are still having difficulty, please let us know.

A few highlights since our last eNews are: 

Darwin

  • The structural works on the Elizabeth River Bridge were completed in December.
  • Work on mud removal and replacement at Berrimah Yard has recommenced.
  • Latest employment figures show 313 Darwin residents are directly employed on the construction of the railway.
Katherine

  • The latest employment figures show 242 Katherine residents are directly employed on the construction of the railway.
  • 310km of track is now complete to the south of the town and 28 kms to the north. Tracklaying south from Katherine was completed with the joining of the track between Katherine and Tennant Creek on 13 December. 
  • Earthworks and drainage in the KR section north of Katherine were completed during December.
  • Tracklaying north will recommence from Katherine towards Darwin in April.
  • Approximately 982,000 tonnes of ballast (82%) have been produced at the Witte Quarry and the production of sleepers reached 563,000 of the total 883,000 required.
Tennant Creek

  • Latest employment figures show 138 Tennant Creek residents are directly employed on the construction of the railway.
  • Tracklaying north from Tennant Creek was completed with the welding of the track between Katherine and Tennant Creek on 13 December. 
  • 363km of track is now complete to the north of the town and 28 kms south.
  • 1,210,000 tonnes of ballast (77%) has been produced locally.
  • The 8 November issue of Tennant & District Times featured an interesting article, by Paul Milton Butler, on the sleeper factory in Tennant Creek.  More information
Alice Springs

  • Over 97,000 tonnes of rail has so far been delivered to the Roe Creek Logistic Centre by rail from OneSteel Whyalla SA to be trucked north to Tennant Creek and Katherine depots.
  • Earthworks and Rock Crews have relocated to the ASR section to continue clearing and blasting works, with 3 camps operating to accommodate workers in the section.
  • The latest employment figures show 54 Alice Springs residents are directly employed on the project. 
South Australia

  • $60 million Contract awarded to EDI Rail. More Information
  • At present 121 South Australians are directly employed on the construction of the railway.
  • South Australia industry has so far been awarded contracts valued at over $329 million.


JOINING OR LEAVING THE RAILWAY eNEWS LIST
If you would like to join our eNews list or know others who would like to join the Railway eNews list, they can join through our website or by sending us an email at rail@aarc.com.au and place word SUBSCRIBE in the subject field. If you no longer wish to receive updates through the Railway eNews, please send us an email and place the word UNSUBSCRIBE in the subject field.

PRIVACY
Your Privacy is important to us. No names or details in our eNews mailing list are shared with other organisations or used for any purpose other than to provide updates on the railway project and related issues

 

© AustralAsia Railway Corporation Disclaimer/Privacy/Copyright Statement
For text based navigation please use the sitemap | Interpreter service
Last updated:
Friday, 2 May, 2003
Telephone 61 8 8946 9595 Search NTG homepage Online services News Sitemap Feedback